Project #10 Resurface Streets in the Town of Ridgeville

Resurfacing the streets in the Town of Ridgeville. Removal of existing asphalt sidewalks and construction of concrete sidewalks to
A.D.A. Standards.
Total length of sidewalks: 1.63 miles. Total length of resurfacing: 2.79 miles.

PROJECT COMPLETED

ROAD NAME MILES
S-18-279 ACADEMY 0.16
S-18-282 BEACH 0.55
S-18-347 CRAB APPLE 0.07
S-18-348 DORCHESTER 0.13
S-18-740 HORSESHOE 0.2
S-18-5 MAIN 0.41
S-18-174 MILL 0.18
S-18-741 MURRAY 0.21
S-18-77 N. RAILROAD 0.29
S-18-202 NEW 0.06
S-18-203 OAK 0.06
S-18-78 S. MAIN 0.47