Project #9 Resurface Streets to the Town of Harleyville
Resurfacing the streets and roads in and adjacent to the Town of Harleyville. Repavement and reconstruction of deteriorated sections of concrete sidewalk to A.D.A. Standards. Total length of resurfacing: 9.11 miles Total length of sidewalk rehabilitation: 1.74 miles.
PROJECT COMPLETED
| ROAD | NAME | MILES |
| S-18-825 | GREENHILL | 0.99 |
| S-18-474 | HUTTO | 0.14 |
| S-18-66 | JOHN | 0.38 |
| S-18-321 | MILL | 0.38 |
| S-18-153 | N. RAILROAD | 1.01 |
| S-18-28 | BIEDLER FOREST | 6.45 |
| RANGE | 0.26 | |
| WEST | 0.15 |

Before Construction





During Construction



After Construction
Click to view Project Status